Documentation Requirements
All seven steps must be documented in a Risk Management Plan and Risk Register. For major projects, this documentation forms part of the business case and is subject to independent assurance review.
Understanding how to identify, assess, and quantify project risks to develop appropriate contingency allowances for Queensland infrastructure projects.
Risk management is a fundamental component of PCEM-compliant cost estimating. The Project Cost Estimating Manual requires systematic identification, analysis, and quantification of project risks to develop appropriate contingency allowances that reflect the uncertainty inherent in infrastructure projects.
Contingency is not a discretionary buffer or a fund to cover scope changes — it represents the financial provision required to address identified risks that may impact project costs. The PCEM distinguishes between:
The most likely cost assuming everything proceeds as planned with no adverse events.
The base estimate plus contingency to account for identified risks and uncertainties.
Provision for future cost increases due to inflation and market conditions.
For major projects and those requiring Australian Government funding, the PCEM mandates probabilistic risk assessment using Monte Carlo simulation to generate P50 and P90 estimates.
PCEM requires a structured, documented approach to risk management. The first three steps establish the foundation for comprehensive risk identification and analysis.
Define the project context, objectives, constraints, and risk tolerance. Identify key stakeholders and their risk appetite. Establish risk categories and evaluation criteria specific to the project.
Key Activities
Systematically identify all potential risks that could impact project cost, schedule, or quality. Use multiple techniques including risk workshops, checklists, historical data review, and expert consultation.
Identification Techniques
Assess each identified risk for likelihood of occurrence and potential consequence to project cost. Develop probability distributions for probabilistic analysis or assign discrete ratings for deterministic assessment.
Analysis Methods
The remaining steps evaluate identified risks, determine treatment strategies, and quantify the residual financial exposure that forms the basis for contingency.
Evaluate and prioritize risks based on their analyzed likelihood and consequence. Determine which risks require active management and which can be accepted or monitored.
Key Activities
Determine the tolerability of each risk and establish priorities for risk treatment. Compare risk levels against acceptance criteria and stakeholder risk appetite.
Key Activities
Develop and implement strategies to address prioritized risks.
Eliminate the risk by changing project scope or approach.
Shift risk to another party such as a contractor or insurer.
Reduce likelihood or consequence through proactive actions.
Acknowledge the risk and provision contingency for potential impact.
Treatment Plans Must Include: Specific actions, responsible parties, timelines, cost of treatment, and expected residual risk after treatment.
Calculate the residual cost impact of risks after treatment strategies are applied.
Financial Quantification
All seven steps must be documented in a Risk Management Plan and Risk Register. For major projects, this documentation forms part of the business case and is subject to independent assurance review.
PCEM identifies eight primary risk categories that should be considered for all Queensland infrastructure projects.
Risks arising from incomplete or evolving design, scope refinements, stakeholder requirement changes, or discovery of unforeseen conditions during design development.
Common Examples:
Risks from changes to technical standards, government policies, planning scheme amendments, or regulatory requirements during project development or delivery.
Common Examples:
Risks from external stakeholder actions or requirements, including utility authorities, rail operators, councils, environmental agencies, and private property owners.
Common Examples:
Risks arising from changes to project objectives, service requirements, performance specifications, or operational needs as the project develops.
Common Examples:
Risks related to costs borne directly by the principal (government agency), including project management, consultants, permits, approvals, and internal staff costs.
Common Examples:
Risks of schedule extension due to approvals, design, procurement, construction issues, or external factors. Delays often result in escalation costs and extended overheads.
Common Examples:
Risks associated with land acquisition processes, including valuation uncertainties, negotiation outcomes, tribunal determinations, and relocation costs.
Common Examples:
Risks from scope elements not yet identified or quantified in the estimate, often due to incomplete design, unforeseen site conditions, or inadequate investigations.
Common Examples:
The PCEM recognizes two primary approaches to evaluating project risk and developing contingency allowances.
Uses single-point estimates for risk likelihood and consequence through risk matrices or percentage-based contingency factors. Assigns discrete likelihood ratings (rare to almost certain) and consequence ratings (insignificant to severe), then plots risks on a likelihood-consequence matrix.
When Appropriate: Suitable for OnQ Type 3 (routine) projects, early strategic planning estimates, and projects under $10 million where probabilistic analysis is not cost-effective.
Typical Ranges: Planning 50-100% | Concept 25-40% | Development 10-20% | Implementation 5-10%
Uses Monte Carlo simulation with @Risk software to model the full range of possible cost outcomes. Assigns probability distributions to uncertain items, inputs risk events with likelihood and cost impact, defines correlations, and runs 10,000+ iterations to generate P50 and P90 estimates.
When Required: Mandatory for OnQ Type 1 (Major Projects), OnQ Type 2 (Complex Projects), and all Australian Government funded projects over $25 million.
Outputs: P50 & P90 estimates, S-curve distributions, tornado diagrams, and sensitivity analysis.
P50 (50th Percentile): The estimate has a 50% probability of being exceeded and 50% probability of not being exceeded. This represents the "expected value" or most likely cost outcome. P50 is appropriate for internal planning and risk-sharing delivery models.
P90 (90th Percentile): The estimate has a 90% probability of not being exceeded (only 10% chance of cost overrun). This represents a high-confidence budget for funding approvals. P90 is typically required for business cases, government funding submissions, and fixed-price contracts.
PCEM Requirement: Major project business cases must present both P50 and P90 estimates, with clear explanation of the difference representing risk-based contingency.
While every project is unique, PCEM provides guidance on expected contingency ranges based on project maturity and information availability. These ranges apply to deterministic estimates; probabilistic estimates determine contingency through Monte Carlo simulation.
| Project Phase | Design Maturity | Typical Contingency Range | Key Uncertainties |
|---|---|---|---|
| Strategic Planning | 0-10% | ±50% to ±100% | Concept only, no design, high scope uncertainty |
| Concept Phase | 10-30% | ±30% to ±50% | Preliminary design, limited investigations, scope refinement likely |
| Development Phase | 30-90% | ±10% to ±20% | Detailed design progressing, most risks identified, construction methodology defined |
| Implementation Phase | 90-100% | ±5% to ±10% | Complete design, specifications finalized, limited scope uncertainty |
Estimate accuracy improves as projects mature from strategic planning through to implementation. As design progresses and uncertainties are resolved, the range of possible cost outcomes narrows.
This progressive refinement must be reflected in contingency allowances, with higher contingencies in early phases gradually reducing as the project matures and risks are retired.
Sophisticated risk management techniques aligned with PCEM requirements, delivering robust and defensible contingency allowances.
Structured risk identification workshops covering all eight PCEM risk categories, bringing together design, construction, procurement, and stakeholder expertise for comprehensive risk capture and aligned treatment strategies.
Licensed @Risk software with qualified analysts experienced in probabilistic cost estimating. We model correlations between dependent risks, run sensitivity analyses, and identify key cost drivers requiring management attention.
Comprehensive risk registers documenting assessment, treatment strategies, residual exposure, and responsibility assignments. Integrated with cost estimates for ongoing risk monitoring and contingency drawdown tracking.
PCEM-compliant probabilistic estimates with full supporting documentation including S-curves, tornado diagrams, and sensitivity analysis for business case submissions and independent assurance reviews.
With CE1 pre-qualification and extensive experience in probabilistic cost estimating for Queensland major projects, Cenex delivers risk-adjusted cost estimates that meet all PCEM requirements while providing actionable insights for project risk management.
Current licenses for Monte Carlo simulation and probabilistic analysis
Team members with specialized training in infrastructure risk assessment
Delivering P50/P90 estimates for major and complex projects
Third-party risk assessment and estimate validation
Cenex delivers CE1 pre-qualified, PCEM-compliant cost estimates for Queensland infrastructure projects.